Schedule

May

  • 4 at 3:00 PM: Meeting at MSCD
  • 10 at 1:30 PM: Teleconference
  • 16 at 5:30 PM: Meeting at MSCD
  • 19: Housing final design finished
  • 25 at 5:30 PM: Meeting at MSCD

June

  • 1: FieldSat electronics built
  • 1: Start assembling VideoSat
  • 5–10: Cold test for FieldSat and SolarSat
  • 12: Drop test payload
  • 13: Start assembling housing
  • 20: VideoSat built
  • 30: Housing and entire payload built

July

  • 1–20: Testing/fine-tuning
  • 3–7: Write final LRR presentation
  • 8 at 7:00: Assembly meeting at Jason Igo's house
  • 13 at 5:30: Meeting at MSCD
  • 28 at 1:00 PM: LRR in Boulder
  • 29 at 7:00 AM: Launch day in Deer Trail